TECHNICAL DATA
- Installed Capacity: 700 MW
- Normal Maximum Reservoir Level: 161 m
- Reservoir Area: 66 KM2
- Water Renovation: 03 days
- Extension of the dam: 925 m
- Beginning of construction: June / 2014
- Beginning of operation: May / 2018
- Deadline until the beginning of the fill up: 36 months
- Regime: water thread
- Spillway: 3 sluices
- Turbines: 04 unity of Kaplan type
- Reservoir Water Volume: 577,22 hm³
- Line Transmission: 40 Km