TECHNICAL DATA
   

  • Installed Capacity:    700 MW
  • Normal Maximum Reservoir Level:    161 m
  • Reservoir Area:    66 KM2
  • Water Renovation:    03 days
  • Extension of the dam:    925 m
  • Beginning of construction:    June / 2014
  • Beginning of operation:    May / 2018
  • Deadline until the beginning of the fill up:    36 months
  • Regime:    water thread
  • Spillway:    3 sluices
  • Turbines:    04 unity of Kaplan type
  • Reservoir Water Volume:    577,22 hm³
  • Line Transmission:    40 Km